Progress billing is a way of invoicing a long job in installments as the work advances, instead of waiting until it is finished. Each invoice, often called a draw or pay application, bills either the share of work completed since the last one or a fixed amount tied to a milestone. On many construction contracts, the customer holds back a percentage of each draw as retainage until the end.
Progress billing is the practice of invoicing a customer in stages over the life of a project, based on the percentage of work completed or on agreed milestones. Each progress bill compares the work billed to date with the contract value and shows what is now due after any retainage, so the customer pays for the job as it is built.
Why long jobs need it
On a project that runs for months, the contractor pays for labor and materials every week. Waiting for a single invoice at the end would mean financing the entire job, and carrying the risk that a customer who runs into trouble halfway through never pays for any of it. Progress billing matches cash coming in to costs going out. It also gives both sides a regular check on whether the job is on budget, because each draw compares what has been billed with what has been built.
Percent-complete vs milestone billing
Most progress billing uses one of two methods, set in the contract before work starts.
| Percent-complete billing | Milestone billing | |
|---|---|---|
| What triggers a bill | A calendar date, usually monthly | Completion of a defined stage |
| How the amount is set | Percentage of each line of work completed, priced from a schedule of values | A fixed amount or percentage agreed for each milestone |
| Best for | Large commercial projects with many trades | Smaller jobs with a few clear stages |
| Main source of disputes | Whether the percentages claimed are accurate | Whether a milestone is really complete |
The schedule of values
Percent-complete billing starts with a schedule of values: the contract price broken into lines for each part of the work, agreed before the first draw. On many US commercial projects the draw is submitted on the American Institute of Architects' G702 Application and Certificate for Payment, with the G703 continuation sheet carrying the schedule of values. AIA describes G703 as breaking the contract sum into portions of the work, and says the two forms together show the status of the contract sum to date so the architect can certify the payment due. AIA notes that it doesn't publish a standard schedule of values form, so the line breakdown is up to the parties.
Whatever form you use, the schedule of values decides how easy every later draw will be. Lines that match how the work is actually done, trade by trade or area by area, make the percentage claims easy to check. A schedule that loads too much value into early lines (sometimes called front-loading) tends to be spotted by experienced owners and can sour the relationship from the first pay application.
Worked example: a percent-complete draw with retainage
Say a general contractor has a $480,000 contract for a commercial tenant fit-out. The contract calls for monthly pay applications and 10% retainage on each draw. The retainage rate here is hypothetical; yours is whatever your contract and the applicable law set. This is draw 3.
| Line of work | Scheduled value | Complete to date | Work completed to date |
|---|---|---|---|
| General conditions | $48,000 | 40% | $19,200 |
| Demolition | $24,000 | 100% | $24,000 |
| Framing and drywall | $96,000 | 75% | $72,000 |
| Electrical | $84,000 | 50% | $42,000 |
| Plumbing | $42,000 | 60% | $25,200 |
| HVAC | $72,000 | 30% | $21,600 |
| Finishes | $114,000 | 0% | $0 |
| Total | $480,000 | 42.5% | $204,000 |
The amount due on draw 3 comes from the cumulative figures, not from this month's work alone:
- Work completed to date: $204,000.
- Retainage at 10%: $204,000 × 10% = $20,400.
- Earned less retainage: $204,000 − $20,400 = $183,600.
- Less previous draws certified: draws 1 and 2 covered $132,000 of work, billed at $132,000 × 90% = $118,800.
- Current payment due: $183,600 − $118,800 = $64,800.
Working cumulatively has a practical advantage. If a percentage was overstated last month and is corrected this month, the correction flows through automatically, and the total billed to date always ties back to the schedule of values.
How retainage works
Retainage (also called retention) is the share of each progress payment the customer holds back until the job is finished, as security that the work will be completed and defects put right. In the example, the owner is holding $20,400 after draw 3. If the rate stays at 10% for the whole job, it will be holding $48,000 by the final draw, all of it money the contractor has earned but cannot yet collect.
The rate and release terms come from the contract, and on some projects from law as well. On federal fixed-price construction contracts, for example, the FAR payment clause lets the contracting officer retain up to 10% of a payment only when satisfactory progress has not been made, and authorizes payment in full when it has. A private contract sets its own retainage terms, so read that clause before you price the job, and ask an attorney whether any state prompt payment or retainage rules apply to it.
Three habits keep retainage from being forgotten:
- Track retainage receivable separately from ordinary receivables, by job, so it doesn't disappear into the general balance.
- Note the release condition in the job file at the start, whether it is substantial completion or a set period after acceptance.
- Invoice the release as its own bill the day the condition is met, with whatever closeout documents the contract requires.
Milestone billing for smaller jobs
A schedule of values is more than most residential or light-commercial jobs need. Milestone billing ties each invoice to a visible stage. Say a pool builder signs a $72,000 contract with this schedule:
| Milestone | Share | Amount |
|---|---|---|
| Contract signed | 10% | $7,200 |
| Excavation complete | 25% | $18,000 |
| Shell complete | 30% | $21,600 |
| Plumbing, equipment and tile complete | 25% | $18,000 |
| Final finish and handover | 10% | $7,200 |
| Total | 100% | $72,000 |
Define each milestone in words a homeowner can verify ("shell complete" should say what that means), and keep the amounts roughly in line with the cost of each stage, so the builder is never far ahead of its payments. The first line is effectively a deposit, and the same rules apply; our guide to deposit invoices covers them, including checking whether any legal limit applies to upfront payments for home improvement work.
Collecting each draw
A progress bill that is approved late or paid late defeats the purpose. The steps below keep draws moving.
- Submit on the contract date every time. Many owners and lenders process pay applications on a fixed monthly cycle. Miss the cutoff and the draw waits a month.
- Attach the backup with the first submission. Include delivery tickets for stored materials and any lien waivers the contract or lender requires. Each missing document is a reason to send the application back.
- Agree the percentages before you submit. A short walk-through with the owner's representative before the pay application goes in settles disputes while they are small.
- Make the draw payable electronically. Large draws are often paid by ACH. Give the customer a payment link on each invoice so a smaller draw can be settled the day it is approved. Invoices that accept partial payments help when an owner approves part of a draw and disputes a line.
- Follow up against the payment terms. Once a draw is approved, chase it on the same schedule as any invoice; our guide to getting paid faster sets out a sequence.
Overbilling and underbilling
Because progress bills are based on estimates of completion, what you have billed rarely equals what you have earned at any moment. Billing ahead of the work done is overbilling; billing behind it is underbilling. Both show up on a work-in-progress schedule, which compares billings to date with the revenue earned on each job. Persistent underbilling means you are financing the job yourself. Heavy overbilling can mean a cash shortfall later, when the remaining work costs more than is left to bill. Your accountant can set up the work-in-progress report and explain how it feeds your financial statements. For the broader picture of deposits, draws and final payment across a contracting business, see invoicing for contractors.